What are small-scale works permits?

As you will see from the analysis below, the procedures for issuing a small-scale works permit are a real maze. Issuing one becomes complicated when, case by case, we look at the categories and subcategories of documents and procedures required each time. The owner has to find their way through a jumble of information.

Everyone involved needs help to understand which category they fall into, or the cost of issuing the corresponding permit. That’s where we come in to make things easier for you!

When is a small-scale works permit required?

According to the legislation (art. 29 Law 4495/17) there are 32 specific categories of works that require a small-scale works permit in 2026:

Examples include the following:

a) trial trenches and excavation following a document from the archaeological service. Approval is not required when the trial trenches are carried out by the competent services of the Ministry of Culture and Sports,
b) installation of prefabricated houses, where special programmes provide for meeting the housing needs of disadvantaged and special population groups
c) pumping installations and structures with the absolutely necessary dimensions to house them, in accordance with article 3 of the Presidential Decree of 24.5.1985, provided they have the required approval of the competent Directorate of Agriculture, except where the construction of columns is required,
d) construction of underground cemetery facilities, such as an ossuary, sunken bins and a water tank, with a maximum area of twenty-five (25.00) sq.m. and a depth of up to four (4.00) m, served by compact external plant-room systems if required, provided that the height of the structures does not exceed one (1.00) m above the final ground level at any point. The installation requires a declaration by a competent engineer who takes responsibility for the structural and electromechanical safety of the structure and installations
e) installation of temporary structures under para. 74 of article 2 of Law 4067/2012, accompanied by a structural adequacy certificate,

In which cases a small-scale works permit is NOT required

According to Ministerial Decision YPEN/DAOKA/69701/4461, Government Gazette B’ 4520/16.10.2018, which supplemented the regime previously established by earlier legislation

In the cases of para. 2 of this article, approval of small-scale building works (EEDMK) without a building permit is allowed, provided that:

  1.  planning regulations are not violated,
  2. the plots, land or structures on which the works are carried out are not located:
  3. in a forest,
  4. in a stream,
  5. on the foreshore or the beach,
  6. in a designated archaeological site where building is prohibited,
  7. in an area of absolute protection,
  8. in an approved public space of the town or settlement,
  9. in buildings that are structurally dangerous, before the danger has been removed,
  10. in a part of a building constructed after the establishment of a roadside arcade and falling within it,
  11. in buildings affected by street-alignment plans, subject to para. 3 of article 41 of Law 4495/2017,
  12. along international, national, provincial, municipal or community roads within a zone 50% of the width defined by the legislation on interurban transport safety.

Find out the exact cost now from Fouskas Construction

CALL US

EMAIL

VISΙΤ US

OPENING HOURS

When is it permitted to carry out small-scale building works?

a. In lawfully existing buildings, as defined in para. 1 of article 23 of Law 4067/2012 (Government Gazette 79 A’),

b. In buildings or parts of buildings that have been included under any law exempting them from demolition or regularising unauthorised constructions (such as Laws 3775/2009, 3843/2010, 4014/2011, 4178/2013 and 4495/2017) and have been definitively exempted from demolition, or have submitted a final regularisation declaration, or have completed the relevant procedure and paid thirty per cent (30%) of the single special fine for unauthorised construction, and

c. In buildings affected by street-alignment plans, where the works fall under cases h, m, s and u of para. 2 of article 29 of Law 4495/2017. For plots affected by street alignment, where works are requested on the unaffected part, these are permitted provided that the affected part is ceded for public use, and the deed of cession must be submitted as a special supporting document.

To be granted approval for small-scale building works the following documents are submitted to the information system:

a. An application by the owner or the person with a legal right, stating their full details and the details of the property.

b. Approvals from the competent services and collective bodies (such as the Ministry of Culture and Sports, the Architecture Council, etc.) where required by current provisions, with their supporting documents.

Learn everything about the process of issuing Small-Scale Works Permits

What are small-scale works permits?

As you will see from the analysis below – and as anyone can easily conclude – the procedures for issuing a small-scale works permit are a real maze, which becomes even more complicated when, case by case, we look at the categories and subcategories of documents and procedures required each time. The owner has to work out which category they fall into amid a jumble of information. And of course, that is no easy task.

Approval of Small-Scale Building Works is the administrative act issued by the Building Department of the competent Municipality that allows the building works in the cases described in more detail below to be carried out, in accordance with the relevant studies prepared by a competent engineer. The basic precondition is that these works must comply with the applicable legislation and the budget of each project must not exceed a specific amount set by the competent authorities.

The Small-Scale Works Permit is a form of building permit that covers smaller works than a full building permit and is issued through the Electronic Permit Issuing System of the Technical Chamber of Greece. As mentioned above, its official name is Approval of Small-Scale Works. It is generally known that any work carried out must be notified to the competent planning authority, whether it is a large industrial plant or simply painting a wall. The planning authority must know about every type of work being done and, in order to be legally covered, you must have obtained the corresponding permit. Our company is here for you, with respect and reliability, to answer every question about the works you want to carry out and to handle the issuing of small-scale works permits.

Once the necessary stages for issuing the permit have been completed, other relevant public authorities, such as IKA (social insurance) and the Police, are notified. Essentially, we are talking about a procedure – an administrative act – that allows all the works listed below to be carried out. A basic precondition for issuing this permit is that the budget must not exceed €25,000. The Approval of Small-Scale Works, or Small-Scale Works Permit, concerns smaller-scale projects and is the permit mainly required for renovations and minor interventions.

In addition, the “Approval of Small-Scale Building Works” was introduced to simplify the permitting process for a list of works for which saving time and money has always been desirable for the applicant. The differences between small-scale works permits and building permits are very clear. In short, being exempt from a very large part of the studies that a Building Permit would require, from the payment of state contributions and from checks of the submitted documents by staff of the competent Building Departments (formerly Town Planning Offices) means that the difference in issuing time and cost is very large compared with Building Permits.

 

When is a small-scale works permit required? 

According to the legislation (art. 29 Law 4495/17), there are 32 specific categories of works that require a small-scale works permit, which you will find in detail below:

  1. Trial trenches and excavation following a document from the archaeological service. Approval is not required when the trial trenches are carried out by the competent services of the Ministry of Culture and Sports,
  2. Installation of prefabricated houses, where special programmes provide for meeting the housing needs of disadvantaged and special population groups or for self-housing of repatriated persons,
  3. Pumping installations and structures with the absolutely necessary dimensions to house them, in accordance with article 3 of the Presidential Decree of 24.5.1985, provided they have the required approval of the competent Directorate of Agriculture, except where the construction of columns is required,
  4. Construction of underground cemetery facilities, such as an ossuary, sunken bins and a water tank, with a maximum area of twenty-five (25.00) sq.m. and a depth of up to four (4.00) m, served by compact external plant-room systems if required, provided that the height of the structures does not exceed one (1.00) m above the final ground level at any point. The installation requires a declaration by a competent engineer who takes responsibility for the structural and electromechanical safety of the structure and installations.
  5. Installation of temporary structures under para. 74 of article 2 of Law 4067/2012, accompanied by a structural adequacy certificate,
  6. Construction of a lift, in accordance with para. 2 of article 27 of Law 4067/2012, required for the movement of people with disabilities or reduced mobility in existing buildings, or in buildings with a lift whose internal car dimensions do not meet ELOT EN 81-70, or in buildings where the lift stops must be extended to serve people with disabilities or reduced mobility,
  7. Felling trees within approved town plans or Residential Control Zones (ZOE), as well as in settlements pre-dating Legislative Decree 17.7.1923 (A’ 223) and settlements delimited by the Presidential Decree of 24.5.1985. Specifically, for felling trees in a public space of a town or settlement, an Approval of Small-Scale Works is granted following an application accompanied by a Technical Report from the competent geotechnical scientist and the competent service of the municipality, and a relevant decision of the competent municipal body, subject to forestry legislation,
  8. Underground natural gas distribution or metering and regulating stations,
  9. Erection of scaffolding. In this case, a project health and safety plan and file must be submitted, appointing the responsible coordinator in accordance with Presidential Decree 305/1996 (A’ 305), together with a declaration by an engineer accepting responsibility for supervising the project,
  10. Installation of site cabins,
  11. Excavation of cable trenches within the land or plots of fuel stations for installing inflow-outflow systems,
  12. External painting, replacement of railings, repair of render or repair of façades using scaffolding,
  13. Façade cladding and replacement of glazed curtain walls using scaffolding,
  14. Construction of a pergola with an area of more than fifty (50) sq.m. in open spaces, front gardens and ground-floor verandas. On roof terraces, outdoor areas and open balconies, approval of small-scale building works is required regardless of area,
  15. Installation of an uncovered water tank or swimming pool with a maximum area of fifty (50) sq.m., served by compact external plant-room systems, provided that no reinforced concrete wall is required for their installation, that the height of the structures does not exceed one (1.00) metre above the final ground level at any point, that no excavation or backfilling of natural ground deeper than one and a half (1.50) metres is required for their installation, and that the planting of the mandatory open space required by current provisions is carried out,
  16. Ventilation ducts and other installations and structures referred to in paragraphs 2b, 2d, 2f and 3 of article 19 of Law 4067/2012,
  17. Internal layout changes, provided that the elements of the building’s load-bearing structure are not affected,
  18. Construction of green roofs and planted surfaces,
  19. Installation of external thermal insulation or passive solar systems on external façades,
  20. Maintenance and repair of roofs using scaffolding,
  21. Simple stone boundary walls up to one (1.00) metre high, or lightweight fencing of land in areas outside the town plan and in settlements without a town plan. For land designated for detention centres for irregular migrants, no approval of works is required, even if the fencing uses any material and a tie beam,
  22. Fencing with a makeshift structure, such as wire mesh, on plots within the town plan that are not affected by street alignment,
  23. Construction of one single stone-built storeroom per cultivated farm, in accordance with para. 4 of article 6 of the Presidential Decree of 24.5.1985, with an area of up to fifteen (15) square metres and a total height including the roof of up to three (3.00) metres, provided that no reinforced concrete is used for its roof and it is built independently of any existing main building, following approval by the competent Directorate of Agriculture, subject to the above provision of the Presidential Decree of 24.5.1985,
  24. Construction of hearths and ovens with their chimneys for professional use, with a technical report by a competent engineer confirming that the load-bearing elements are not affected,
  25. Construction of fireplaces with their chimneys in independent residential properties, provided that an engineer’s technical report confirms that the structural adequacy of the building’s load-bearing structure is not affected,
  26. Reconstruction of a roof, with a structural adequacy declaration by a competent engineer,
  27. Functional merging of spaces in accordance with para. 5 of article 23 of Law 4067/2012,
  28. Addition of an area of up to five (5) sq.m., exclusively for hygiene and usability reasons, to buildings pre-dating 31 January 1983, in static settlements and settlements pre-dating 1923 with fewer than two thousand (2,000) inhabitants, without requiring proof of the building’s legality,
  29. Installation of external thermal insulation or roof insulation under the “Exoikonomisi kat’ oikon” (Energy Saving at Home) programme,
  30. Installation of an autonomous heating system,
  31. Canopies and awnings under paragraphs 72 and 79 of article 2 of Law 4067/2012,
  32. Interventions on building façades to modify existing openings or create new ones, provided that the load-bearing structure is not affected and the interventions do not conflict with more specific provisions.

Approval of small-scale works is also required for carrying out works where this is provided for in more specific provisions, as well as for legalising any work that requires the issue of a relevant administrative act.

Small-Scale Works Approvals (E.E.M.K.) are generally issued quickly. You can contact us and we will inform you in detail about the exact time needed to issue a small-scale works permit for your project.

In which cases a small-scale works permit is NOT required

According to Ministerial Decision YPEN/DAOKA/69701/4461, Government Gazette B’ 4520/16.10.2018, which supplemented the regime previously established by earlier legislation, in the cases of para. 2 of this article the approval and execution of small-scale building works (EEDMK) is allowed, without a building permit, in lawfully existing buildings, as well as in buildings or parts of buildings that have been exempted from demolition or included under any law exempting them from demolition or regularising unauthorised constructions, provided that:

a. planning regulations are not violated,

b. the plots, land or structures on which the works are carried out are not located:

  • in a forest,
  • in a stream,
  • on the foreshore or the beach,
  • in a designated archaeological site where building is prohibited,
  • in an area of absolute protection,
  • in an approved public space of the town or settlement,
  • in buildings that are structurally dangerous, before the danger has been removed,
  • in a part of a building constructed after the establishment of a roadside arcade and falling within it,
  • in buildings affected by street-alignment plans, subject to para. 3 of article 41 of Law 4495/2017,
  • along international, national, provincial, municipal or community roads within a zone 50% of the width defined by the legislation on interurban transport safety.

For the Approval of Small-Scale Works (Small-Scale Works Permit), the project must also be declared to IKA (social insurance) and the corresponding insurance contributions paid.

When is it permitted to carry out small-scale building works?

a.) in lawfully existing buildings, as defined in para. 1 of article 23 of Law 4067/2012 (Government Gazette 79 A’),

b.) in buildings or parts of buildings that have been included under any law exempting them from demolition or regularising unauthorised constructions (such as Laws 3775/2009, 3843/2010, 4014/2011, 4178/2013 and 4495/2017) and have been definitively exempted from demolition, or have submitted a final regularisation declaration, or have completed the relevant procedure and paid thirty per cent (30%) of the single special fine for unauthorised construction, and

c.) in buildings affected by street-alignment plans, where the works fall under cases h, m, s and u of para. 2 of article 29 of Law 4495/2017. For plots affected by street alignment, where works are requested on the unaffected part, these are permitted provided that the affected part is ceded for public use, and the deed of cession must be submitted as a special supporting document.

WORKS WITHOUT A PERMIT under Law 4495 are:

  • Interior painting, minor repairs to doors and windows, or individual repairs for reasons of use and hygiene.
  • Minor interior repairs or alterations that do not change the load-bearing structure of the building.
  • Structures required for the movement or any form of assistance of people with disabilities or reduced mobility. This does not include the construction of a lift.
  • External painting, replacement of railings, repair of render or repair of façades without using scaffolding.
  • Replacement of interior or exterior windows, doors and glazing within the same opening.
  • Maintenance and repair of roofs or roof terraces without using scaffolding.
  • Installation of air conditioners and wall-mounted gas boilers for heating and domestic hot water in existing buildings.
  • Installation of solar water heaters.
  • Installation of passive solar systems, replacement of external windows and doors, or installation or replacement of chimneys on the external façades of existing buildings, without using scaffolding, under the “Exoikonomo kat’ oikon & Exoikonomo Aftonomo” programme, as well as installation of passive solar systems, replacement of external windows and doors, or installation or replacement of chimneys on the external façades of existing buildings without using scaffolding.
  • Placing or installing equipment in buildings, such as wardrobes and planters, changing, installing or removing balcony partitions, and installing small permanent decorative
    and functional elements, such as statues, fountains, shrines, benches and tables, or makeshift animal shelters with an area of up to three (3) sq.m. in the open spaces of plots and land.
  • Construction of hearths, ovens and fireplaces with their chimneys in the open spaces of plots or land, provided there is a residential building, as well as in a building that has a building permit or exists lawfully, provided that the load-bearing elements of the residential building are not affected.
  • Construction of a pergola, with or without temporary shades, with an area of up to fifty (50) sq.m., in open spaces, front gardens and ground-floor verandas, provided this is not prohibited by special provisions applicable in the
    area.
  • Structures such as stairs, ramps, buttresses and low walls in the open spaces of plots and land.
  • Installation of temporary shades, louvres, canopies and awnings.

Renovation and issuing a small-scale works permit

In most cases of renovating your building or your home, a small-scale works permit is required. However, if the works are limited to simple painting without scaffolding, laying tiles, replacing sanitary ware, replacing windows and doors without changing their dimensions, or installing air conditioners, solar water heaters and wall-mounted boilers, without changes to the internal layout, no Approval or Permit is required.

Finally, if the internal layout changes are quite extensive, the project budget exceeds twenty-five thousand (25,000.00) euros as mentioned above, or there are interventions in the load-bearing structure (frame) or the central pipework of the apartment building’s installations, then a Building Permit is required. After all, a radical renovation is a significant process involving a wide range of works, and it is often carried out in order to completely reshape and re-arrange the existing space.

The Small-Scale Works Permit under Law 4495 is therefore necessary in renovations and construction. The permit is required for many building works, and in order to be fully covered – including with regard to noise, debris removal and other phases of a renovation that may disturb your neighbours – it is wise and necessary to have taken all legal measures. In a renovation, the company you choose, if it is made up of professionals, will fully inform you about all the necessary legal procedures and planning approvals before you start any work.

To issue a Small-Scale Works Permit, you need a professional engineer or a registered architect who must prepare construction drawings and submit the necessary documents.

The state has divided permits for building works into two main categories.

  1. New construction works, which (generally) require a building permit, i.e. a full building permit with all the necessary studies.
  2. Minor works, which require a small-scale works permit.

There are many cases in which renovations require a Small-Scale Works Permit, and obtaining one is important and beneficial because:

  • It ensures the proper, uninterrupted flow of the works.
  • It protects you from complaints and legal penalties (fines).
  • It ensures the necessary social insurance (IKA) stamps for workers.

The most common works requiring a Small-Scale Works Permit when renovating an apartment are:

  • Works using scaffolding
  • Demolition of interior walls
  • Façade cladding and replacement of glazed curtain walls

What documents are required?

Issuing a Small-Scale Works Approval requires two kinds of documents:
1. The General Documents, which are included in the application file regardless of the type of works to be carried out
2. The Special Documents, which depend on the type of works you will carry out.
According to article 41 para. 1 of Law 4495/17, the following documents are submitted to the information system to obtain approval for small-scale building works:

a. An application by the owner or the person with a legal right, stating their full details and the details of the property.

b. Approvals from the competent services and collective bodies (such as the forestry office, the Ministry of Culture and Sports, the Architecture Council, etc.) where required by current provisions in each case, with their supporting documents.

c) An engineer’s technical report and project budget.

d) Proof of submission of a declaration to the Cadastre, or a certificate for a property registered in the Cadastre, or an extract of the cadastral diagram or, failing that, the topographic plan attached to a legal deed, or the plan of the building permit.

e) Photographs of the property.

f) A copy of the building’s building permit, if there is a building or structures. In the case of structures or divided properties that have been included under any law exempting them from demolition or regularising unauthorised constructions, a certificate of exemption or completion is submitted from the competent authority that issued the act or the competent Building Department, or a certificate of completion of the inclusion procedure from the TEE electronic system, or a certificate of payment of thirty per cent (30%) of the single special fine from the TEE electronic system, depending on the provisions of the law under which they were included.

g) A declaration of consent from the co-owners of the property, if the works are carried out in common areas, such as the open spaces of the plot or land, or jointly owned parts of the building, such as façades, the load-bearing structure, the roof terrace and the roof.

Issuing an Approval of Small-Scale Works requires an engineer, who will gather the necessary documents and submit the file. While in general Small-Scale Works Permits do not require a supervising engineer for the works, the exception is the erection of scaffolding. In this case, a Health and Safety Plan (SAY) and Health and Safety File (FAY) must be prepared, and the erection and removal of the scaffolding must be supervised by an engineer.

In more detail:

The documents and details required from the owner of the project to be permitted vary depending on the case and the specific Small-Scale Works category the project falls under; however, some of the required documents are common to all cases.

Therefore, regardless of the specific Small-Scale Works Permit case, the following are always required:

  1. The full details of the applicant / owner of the project: full name, father’s name, mother’s name, type and percentage of ownership right, home address, ID card number, tax number (AFM), tax office (DOY), contact details (phone, email),
  2. The property’s title deeds together with a recent certificate of ownership, as well as any notarial declarations of designated parking spaces,
  3. The Cadastral Sheet and Diagram of the property,
  4. The Private Lease Agreement, if the owner of the project is the tenant of the property (always provided that the lease expressly states that the tenant has the right to carry out the works in question and obtain permits for them),
  5. If the works are not to be carried out on an existing building: full details of the older Building Permits issued for the building: the permit sheet, the approved Topographic Plan, approved drawings and documents of other studies (Architectural Plans, Sections, Elevations, Coverage Diagram, Structural, Mechanical, Plumbing, Drainage), approved Technical Reports, etc., as well as full details and drawings of any Regularisations carried out under the Unauthorised Constructions Laws (Laws 3843/10, 4014/12, 4178/13, 4495/17 or earlier).
  6. The studies to be prepared and other documents within the remit of the Engineer(s) handling and issuing the Permit are also considered required documents. These may include a Topographic Plan, Building Diagram, Architectural Study, Structural Study, Electromechanical and Plumbing Installation Studies, Energy Performance Study, Fire Protection, Fuel Gas, Health and Safety Plan, Waste Management Plan, Technical Reports, Certificates, etc.

In addition to the above documents, which are mandatory in all cases of Approval of Small-Scale Works, some additional documents are required depending on the category, and these may be:

  1. Possible approvals from competent public services, such as Archaeological Services, Architecture Councils, the Forestry Service, the Civil Aviation Authority, the Council for Planning Issues and Disputes, the National Telecommunications and Post Commission, the Directorate of Agricultural Development and Food, etc.,
  2. Solemn declarations by the Engineer on Structural Adequacy or proper functioning of Electromechanical Equipment,
  3. Declarations of consent from co-owners for works in common areas,
  4. Technical reports or solemn declarations from other professionals, such as agronomists, or measurements by certified laboratories,
  5. Operating licences of the business based in the property, or installation approvals for mechanical equipment such as telecommunications antennas,
  6. Decisions on funding programmes,
  7. Private agreements between owners, etc.

The process of issuing a Small-Scale Works Permit

The process of issuing a Small-Scale Works Permit is similar to that for a Building Permit, except that fewer studies and documents are required. As a result, it is issued much more quickly. However, you should pay particular attention to the issuing process. It often happens that an Approval of Small-Scale Works is issued and then additional works are carried out that require a full Building Permit – which, apart from wasting time and effort, can also cost you unnecessary expenses.

It is therefore particularly important for the competent engineer to inform you properly from the start about the restrictions that apply, to avoid doing the work twice if an additional Building Permit is needed. The engineer should therefore make a thorough study of your space, listen to the works and changes you want to make and, finally, inform you about the permits that need to be issued.

According to article 29 of Law 4495/17, the process of issuing an Approval of Small-Scale Building Works consists of the following stages:

First stage: The applicant specifies exactly which works / structures they want to carry out on their property and in which areas.

Second stage: Contact with our company and a visit to the property for a survey, photographs (if required) and our determination of the legislative framework that covers the desired works / structures from a planning perspective.

Third stage: Preliminary study and development of architectural solutions according to each case and the particular characteristics of each project, with a detailed and thoroughly documented presentation to the client.

Fourth stage: The client hands over to us all the required documents relating to the property (ownership documents, copies of previous Building Permits, inclusions under Unauthorised Construction Laws, etc.) and a complete file is created.

Fifth stage: Preparation of all the required studies for the project in accordance with the applicable regulations (Building Code, Building Regulations, Seismic Code and Concrete Code) by our team of experienced designers and engineers. Our goal is always to offer you top services in a short time, while always respecting your needs.

Sixth stage: Submission of the documents and studies to the competent Building Department through the e-adeies electronic system and/or to any other services whose approval may be required in each case (Architecture Council, Archaeological Services, etc.). Applications for approval of small-scale building works are submitted electronically under the responsibility of the submitting engineer, and the approval is issued automatically, immediately after the electronic submission of the required documents, studies and details.

Seventh stage:  Issue of the Approval after payment of the State fee, and after
the Approval has been issued, the owner of the project has the legal right to start the works. The approval form with its number is published online and the building works may begin.

Permit issue and cost

The cost of a Small-Scale Works Permit differs from case to case and depends on various factors. That’s why it is best to contact your civil engineer, who will be able to give you reliable and detailed information about the process and the cost of issuing the Approval of Small-Scale Works.

An Approval of Small-Scale Works is valid for 1 year, and it is also possible to obtain an extension for another year, subject to conditions in each case.

Approval of Small-Scale Building Works

Approvals of Small-Scale Building Works are issued exclusively through the e-adeies online platform of the Technical Chamber of Greece. The application is managed by a private engineer or company using personal credentials certified by the TEE. The manager submits all the final required details electronically (documents, studies, drawings, solemn declarations, etc.) and, after payment of the State fee (€20.00), the Approval is issued. Approvals of Small-Scale Building Works are spot-checked by the competent Building Department at a rate of 30% after the Permit has been issued, within 6 months of issue.

We hope that all the above details and information have given you a good understanding of small-scale works permits. With many years of experience and knowledge kept up to date with current works and legislation on everything concerning renovations and interventions in buildings and spaces, our company is always at your disposal, with expert knowledge and a reliable network of engineers and professionals.